How long can a utility take to approve home solar? Review deadlines in six jurisdictions and where to complain
A utility that follows the written rules has a fixed number of business days to review a small home solar application: 20 to 35 in the six jurisdictions checked, counted from a complete submission to the written decision. The final step, permission to operate, carries its own day count in only three of them: 30 business days in PG&E's Rule 21 for net metering and net billing systems of 1 MW or smaller, 20 in Maryland, and 13 in Minnesota's Simplified Process (a 10-day witness-test window plus 3 days).
Add every printed step and the sums diverge. PG&E's tariff stacks to 70 business days, about 14 weeks at five business days a week, or 75 if a separate five-day authorization clause follows the 30, before any time the customer, the installer or the inspector spends. Maryland's stacks to 40 and Minnesota's to 33. Washington, Pennsylvania and Illinois print a review deadline and then no day count for the utility's final written sign-off, so one stalled file can be late under one rulebook and still inside the rules under another. Other states' rules and other utilities' tariffs differ, and the six rows below are a sample of rulebooks, not a survey of the country.
Two points hold in all six texts. A missed deadline is not an approval: each clock ends in a notice, a report to the regulator or, for witness tests, a waiver in the customer's favor, and a lapsed clock never produces permission to connect. And where a size limit chooses the track, it is written on rated output, in AC kilowatts or volt-amps, not on the DC panel total printed in the quote, so one roof can land on different tracks depending on the inverter chosen for it.
Review clocks for a small home system
The table below describes one case: a complete application for a certified, inverter-based system of home size, with no utility construction needed. In that case each rule routes the file to its shortest track: Fast Track under PG&E's Rule 21, Tier 1 in Washington, Level 1 in Pennsylvania, Maryland and Illinois, and the Simplified Process in Minnesota. Every rule gives the utility two kinds of deadline, a notice that the application is complete or not and then a decision, and the counts are business days.
Business day is defined in three of the six texts. Washington's chapter says Monday through Friday excluding official federal and state holidays. PG&E's tariff says Monday through Friday, excluding Federal and State Holidays (Section C, sheet 19). Illinois says Monday through Friday, excluding State and federal holidays. Chapter 75 in Pennsylvania, COMAR 20.50.09.02 in Maryland and Sections 1 to 3 of the Minnesota process do not define the term, so those three leave open whether a holiday stops the count.
Each rule binds a defined set of utilities. Washington's chapter applies to electrical companies under the Utilities and Transportation Commission, and the commission's complaint page says that disputes with public utility districts and municipal utilities go to those utilities directly. Rule 21 covers facilities that connect to systems under the California Public Utilities Commission's jurisdiction, and the copy checked is PG&E's own filing. Pennsylvania's subchapter is written for electric distribution companies, Maryland's chapter for utilities and Illinois's Part 466 for electric distribution companies. Minnesota's document is the process the Commission approved, as published by Otter Tail Power; other Minnesota utilities publish their own copies of the process.
| Jurisdiction and rule | Track for a home system | Completeness notice | Written decision | Agreement |
|---|---|---|---|---|
| California, PG&E Electric Rule 21 (sheets 70, 81, 82, effective August 29, 2025) | Fast Track, Initial Review first | 10 business days from receipt (20 with the Cost Envelope Option) | Initial Review result within 15 business days of validation, absent extraordinary circumstances | Generator Interconnection Agreement within 15 business days of the result when no upgrades are needed |
| Washington, WAC 480-108-030(8) | Tier 1 | Receipt notice in 5 business days; complete or incomplete notice 10 business days after that | Approve, approve with conditions or deny within 20 business days of the complete notice | Executable agreement in the same package as the approval |
| Pennsylvania, 52 Pa. Code 75.37 | Level 1 | 10 business days from receipt | Screens verified within 15 business days after the end of those 10 | No day count for sending the agreement |
| Maryland, COMAR 20.50.09.09 | Level 1 | 5 business days from receipt | Screens verified within 15 business days of the complete notice | No day count for sending the agreement at Level 1 |
| Illinois, 83 Ill. Adm. Code 466.90 | Level 1 expedited review | 7 business days from receipt | Screens verified within 15 business days of the complete notice | Conditional agreement sent with the results |
| Minnesota, MN DIP Section 2 (Otter Tail Power copy) | Simplified Process | Within 10 business days of receipt (inside the 20) | Result within 20 business days of receipt of a complete application | Executable agreement within "five (5) days" |
Four details in the wording change how a deadline is counted. Pennsylvania counts its 15-business-day screening period from the end of the 10-business-day completeness window, not from the day the utility actually sends its notice, so a Level 1 file has a fixed outer limit of 25 business days from receipt. Minnesota runs the other way: the 20 business days run from receipt of a complete application and the completeness check falls inside them, so a clean file gets 20, not 30. Washington's review clock starts only when the application and the application fee have both been received. And Pennsylvania's one deadline for a lost request, the evaluation the utility must finish after an applicant shows the original was delivered, is written as 15 days, not 15 business days.
The firmness of the language varies as much as the numbers. Washington says the electrical company shall approve, approve with conditions, or deny within 20 business days, then adds that when delays come from unforeseen circumstances, customer variance requests or other incentive program approval requirements, the customer shall be promptly notified. Its Tier 1 paragraph (a), which lists the single application and the contents of the approval package, also says that deviations from those standard practices are not violations; the timeline is in paragraph (b). PG&E's tariff sets Reasonable Efforts as the standard for its timelines (Section F.1.d) and defines the term in full as "efforts that are timely and consistent with Good Utility Practice and are otherwise substantially equivalent to those a Party would use to protect its own interests" (Section C, sheet 32, effective April 17, 2025). Its result deadline is stated as holding absent extraordinary circumstances. The Pennsylvania, Maryland and Illinois Level 1 paragraphs say shall with no softening clause of that kind.
Approval is not permission to operate
The decision in the first table lets the project proceed toward installation; it does not let the system run. PG&E's Rule 21 requires express written permission before parallel operation. Washington's chapter treats the process as complete only when the agreement is executed, the company has approved the certificate of completion in writing, any required witness test is approved, all required agreements with the balancing area authority and for the purchase, sale or transport of electricity are signed, and permission has been granted to proceed with commercial operation, and the same chapter directs immediate disconnection of an unapproved generating facility. Minnesota's Simplified Process says the customer has no right to operate in parallel, except for optional testing not to exceed two hours, until permission to operate is granted. Illinois's Level 1 contract lets the customer construct, with operational testing not to exceed two hours, once the utility has signed the conditional agreement, and allows operation only after the inspection, the certificate of completion and a completed or waived witness test. The installation process guide separates these two utility decisions as stage 4 and stage 7, and the table below shows which of the six put a number on stage 7.
| Jurisdiction | Written permission required | Utility clock after installation |
|---|---|---|
| California, PG&E Rule 21 | Express written permission before parallel operation (Section D.1, sheet 37) | For NEM-1, NEM-2 and NBT-1 facilities of 1 MW or smaller: Permission to Operate normally within 30 business days of receipt of the complete request and payments, the signed agreement, and final inspection clearance (D.13.b, sheet 45); if not met, notice to the applicant and the Commission with the reason and expected date. Section F.5.b (sheet 126) separately requires written authorization for parallel operation within 5 business days of satisfactory compliance with the terms of all applicable agreements |
| Washington, WAC 480-108-050 | Agreement executed, certificate of completion approved in writing by the company, any witness test approved, permission granted to proceed with commercial operation | No day count in the section |
| Pennsylvania, 52 Pa. Code 75.37(c) | Approval subject to local code approval, certificate of completion, witness test completed or waived, signed agreement | Witness test within 10 business days of the certificate of completion, on notice, or it is deemed waived; no day count for the approval itself |
| Maryland, COMAR 20.50.09.09C | Permission to operate notice (defined as written permission by email or letter) | Within 20 business days of receipt of acceptable documents, subject to four conditions |
| Illinois, Part 466 Appendix A | Inspection, certificate of completion and a completed or waived witness test, after the conditional agreement | Witness test within 10 business days of the commissioning date or it is deemed waived, unless the utility has good cause; no further day count |
| Minnesota, MN DIP 2.3 | Permission to operate notice; no right to operate in parallel before it, except optional testing up to two hours | Witness test within 10 business days of the certificate of completion or it is deemed waived; notice within 3 business days of inspection or waiver |
PG&E's 30 business days apply to net metering and net billing facilities (NEM-1, NEM-2 and NBT-1) of 1 MW or smaller, and they start when three items have arrived: a completed request with its supporting documents and payments, a signed agreement, and evidence of final electric inspection clearance from the local authority. The tariff says the approval shall normally be processed within that period, and when the period cannot be met the utility must tell the applicant and the Commission why and when it expects to finish. Maryland's Level 1 text sets 20 business days from receipt of acceptable documents and then lists four conditions: local code approval, a returned certificate of completion, a completed or utility-waived witness test and a signed interconnection agreement. Both clocks begin at the customer's last document, so a slow inspection sign-off or a missing signature delays the start without breaking any utility deadline.
A second clause in the same tariff puts a shorter clock on the written authorization itself. Section F.5.b (sheet 126, effective August 29, 2025) says the Distribution Provider "shall authorize Producer's Generating Facility for Parallel Operation or Momentary Parallel Operation with Distribution Provider's Distribution or Transmission System, in writing, within five (5) Business Days of satisfactory compliance with the terms of all applicable agreements," and adds that compliance may include required documentation and any required inspections or tests. F.5.b has no size or tariff limit, while D.13 (sheets 44 and 45) opens with "Notwithstanding any other provision in this Rule" and then sets the 30 days for NEM-1, NEM-2 and NBT-1 facilities of 1 MW or smaller. The tariff does not say how the two relate. One reading is that the five days fall inside the thirty, because the Permission to Operate in D.13.b is the same authorization; the other is that the five days start once the utility finds the facility in compliance and so follow the thirty. The first reading leaves the California total at 70 business days and the second makes it 75. D.13.b says the approval shall normally be processed within 30 days and F.5.b says the utility shall authorize within five, so an applicant whose file passes the 30 days without a notice can cite both clauses in the written request.
Where a rule is silent on the timing of the final approval, the witness-test window is the only clock left. Pennsylvania and Illinois give the utility 10 business days to witness the system, counted from the certificate of completion in Pennsylvania (on notice) and from the commissioning date in Illinois, and both treat an unperformed test as waived. Illinois adds an exception, "unless the EDC cannot do so for good cause", in which case the customer agrees to another date within 10 business days after the original. Minnesota uses the same 10 business days and the same waiver. A waived test removes one condition and leaves the others in place: in Pennsylvania the approval is still subject to local code approval, the certificate and the signed agreement.
Washington's chapter is also the rule the DIY installation guide quotes for the certificate of completion, and the point carries over: the certificate is the customer-side document that starts the utility's final step, and in Washington the section that governs that step prints no deadline for it.
Adding up the utility's maximums
The sums below add only steps for which the rule prints a day count, and they stop at any gap. They are utility-side maximums for a clean application with no construction: customer response time, installation, inspection scheduling and signature periods are left out. Business days convert to weeks at five per week with no holidays removed, so the week figures are floors for the calendar time.
| Jurisdiction | Receipt to written decision | Weeks at 5 business days | Agreement step | Final-step clock | Listed total |
|---|---|---|---|---|---|
| Maryland, COMAR 20.50.09 | 20 | 4 | no day count | 20 business days | 40 business days (8 weeks) |
| Minnesota, MN DIP Section 2 (Otter Tail Power copy) | 20 | 4 | 5 days | 10 + 3 business days | 33 business days (6.6 weeks), not counting the 5-day agreement step |
| Illinois, 83 Ill. Adm. Code 466 | 22 | 4.4 | with the results | witness window 10; then no day count | none: a step has no day count |
| California, PG&E Electric Rule 21 | 25 | 5 | 15 business days | 30 business days, plus 5 if F.5.b follows | 70 business days (14 weeks), or 75 (15 weeks) |
| Pennsylvania, 52 Pa. Code ch. 75 | 25 | 5 | no day count | witness window 10; then no day count | none: a step has no day count |
| Washington, WAC 480-108 | 35 | 7 | with the approval | no day count | none: a step has no day count |
Show the bar values as a table
| Jurisdiction | Notice steps (business days) | Review step (business days) | Total |
|---|---|---|---|
| Maryland, COMAR 20.50.09 | 5 | 15 | 20 |
| Minnesota, MN DIP | inside the review | 20 | 20 |
| Illinois, Part 466 | 7 | 15 | 22 |
| California, PG&E Rule 21 | 10 | 15 | 25 |
| Pennsylvania, ch. 75 | 10 | 15 | 25 |
| Washington, WAC 480-108 | 15 | 20 | 35 |
From complete application to written decision, Maryland and Minnesota give the utility 20 business days (4 weeks), Illinois 22, California and Pennsylvania 25 (5 weeks), and Washington 35 (7 weeks). Washington's total is the longest because its rule spends 15 business days on a receipt notice and a completeness notice before the 20-day review begins, and in return the approval arrives with an executable agreement. Maryland's 20 ties Minnesota's for the shortest decision clock, and Maryland also prints a 20-business-day clock for permission to operate.
Only California and Minnesota print a number on every step from submission to the final notice, and California's total, 70 business days (75 on the second reading of F.5.b), is the longest listed: 10 to validate, 15 for the Initial Review, 15 for the agreement and 30 for permission to operate. If the five-day authorization in F.5.b follows the thirty instead of falling inside them, as the section above sets out, the total is 75. That shows the tariff prints the most steps, not that PG&E files run slower than Maryland files; the totals are sums of printed maximums, not measurements of how long any utility takes. Maryland's 40 leaves out the delivery of the Level 1 agreement, which has no day count. It also leaves out .08A, which gives the utility 10 business days to determine jurisdiction and review level; the rule does not say whether that runs before or alongside the 5-day completeness notice. Minnesota's 33 leaves out its five-day agreement step.
Minnesota offers a cross-check on the arithmetic. Put every Section 2 step in worst-case sequence, starting from an incomplete first submission, and the chain is 10 + 5 + 5 + 20 + 5 + 30 + 10 + 3 = 88 business days, counting the agreement's "five (5) days" as 5. Of those, 35 belong to the customer: 5 to supply missing items and 30 to sign. A Minnesota Public Utilities Commission staff presentation from May 19, 2025, which states that it gives the views of the presenters rather than the Commission, puts the Simplified track at roughly 83 to 93 maximum business days with 30 to 40 days on the customer side. The sum above falls inside both ranges.
A Maryland file counted day by day
Hypothetical file, all counts in business days from the day a complete Level 1 application reaches a Maryland utility, which is day 0. The completeness notice is due by day 5 (COMAR 20.50.09.09B(1)). The screening result is due 15 business days after that notice, so no later than day 20. Suppose the installer then builds the system, the local inspector passes it and the customer returns a signed agreement, so that acceptable documents reach the utility on day 60. The permission to operate notice is then due within 20 business days, no later than day 80. The utility's printed maximum for the whole file is 20 + 20 = 40 business days, and the other 40 days between day 20 and day 60 were spent on construction, inspection and signatures, which the rule does not clock.
If the screening result arrives on day 24, it is 4 business days late, and the first written complaint can cite .09B(2) and the date the complete notice was sent. If the applicant files a dispute that day, .13D suspends the deadlines the dispute directly affects until it is resolved, and the rule does not say whether the deadline already missed counts as directly affected.
Size limits are measured at the inverter
Every rule that sets a fast-track size limit defines the measure, and the definitions point at rated output rather than panel watts. Washington's chapter says that for an inverter-based system the nameplate capacity is the manufacturer's AC output rating of the inverters. Pennsylvania's definition is the net maximum or peak output measured in volt-amps of the facility, the inverter or the aggregated capacity of multiple inverters. Minnesota states that capacities in the process are alternating current. Maryland and Illinois define nameplate capacity as the maximum rated output of generators, storage and other power production equipment. The quote's DC panel total is not the number on any of those lines.
| Jurisdiction | Fast-track limit | How output is measured | Next track up |
|---|---|---|---|
| California, PG&E Rule 21 | No kW split in the Fast Track sections cited | For a solar modification in Table F.1, the lesser of inverter nameplate (kW) or maximum solar output (CEC-AC rating) | Supplemental Review within 20 business days after the fee; Detailed Study after that |
| Washington | Tier 1: 25 kW or less, single phase, inverter-based, secondary voltage, no utility construction beyond meters | For inverter systems, the manufacturer's AC output rating of the inverters | Tier 2 (up to 500 kW): decision in 30 business days, agreement offer in 5 more |
| Pennsylvania | Level 1: inverter-based, 10 kW or less, certified equipment | Volt-amps of the facility, the inverter or the aggregated inverters; multiple devices at one point are aggregated (75.36(1)) | Level 2 (up to 2 MW): 10 business days for completeness, then 20 to evaluate (30 from receipt), 5 more for the agreement, extra fault-current screens |
| Maryland | Level 1: inverter-based, 20 kW or less, including multiple facilities at one point of common coupling | Maximum rated output of all power production equipment and energy storage devices at the point of common coupling | Level 2 (up to 2 MW): 5 business days completeness, 20 to evaluate, 5 for the agreement |
| Illinois | Level 1: export 25 kW or less and nameplate 50 kW or less (25 kW nameplate if export is not limited), inverter-based, lab-certified | Maximum rated output in kVA of generators, storage systems and other power production equipment | Level 2: 10 business days completeness, 20 to evaluate, 5 for the agreement when no construction is needed |
| Minnesota | Simplified: certified inverter-based DER of 20 kW AC or less | Alternating current throughout the process | Fast Track: 15 business days for the initial review after the complete notice |
An illustration with a stated input shows what that does. Take a DC to AC ratio of 1.25, a common sizing choice used here only as an input. A 12.5 kW DC array behind a 10 kW inverter is at the Pennsylvania Level 1 line, which is 10 kW or less. A 13 kW DC array at the same ratio needs a 10.4 kW inverter, is above the line, and moves to Level 2. The clock difference is small, 30 business days from receipt to evaluation (10 for completeness, then 20) against 25, plus a 5-business-day agreement clock. The technical difference is larger: Level 2 adds screens on contribution to circuit fault current (10 percent) and on exposure of protective devices to fault current above 85 percent of their interrupting capability, which the Level 1 list does not include.
Storage can count toward the same line. Maryland's and Illinois's definitions name energy storage in rated output, so a battery listed on the application can add to the figure the limit is tested against. Maryland's Level 1 limit is 20 kW, and Illinois's has two parts, 25 kW of export and 50 kW of nameplate, with 25 kW of nameplate if export is not limited. The non-export solar guide covers systems built so that no power crosses the meter. Maryland's Level 3 and Pennsylvania's Level 4 are the tracks these texts write for non-exporting facilities; the Level 1 size tests in both states do not mention export, so a small inverter-based system built not to export can meet them.
Size is only one of the tests. Four of the six rules, Washington, Pennsylvania, Maryland and Minnesota, include a first screen that caps the aggregate generation on the circuit at 15 percent of the line section's annual peak load, and Washington counts projects already in the queue toward it. A street that has filled that headroom can push the next home application off the fast track, whatever the size of the roof. Illinois's Level 1 screen uses a different formula, a limit of 100 percent of the circuit's minimum load after December 31, 2023, and Minnesota's text lets the utility use 100 percent of applicable loading, such as daytime minimum load for solar, in place of the 15 percent figure.
What pauses, resets or ends a file
Five things move a file off its clock. The first is an incomplete application. California gives the customer 10 business days to cure a first deficiency notice and 5 after a second, plus one extension of up to 20, and deems the request withdrawn if the deficiencies stay; Illinois gives 10 business days; Minnesota gives 5 and the utility 5 more to review the added material; Washington gives 15 and lets the company extend in writing. The Level 1 paragraphs in Pennsylvania and Maryland require the utility to say what is missing and print no customer deadline for supplying it.
| Jurisdiction | Customer-side limits | What resets or extends the review | What ends the file |
|---|---|---|---|
| California, PG&E Rule 21 | 10 business days to cure a first deficiency notice, 5 after a second; one extension of up to 20 | One modification request, handled in 10 business days (20 if a re-study is needed); changes outside Table F.1 need a new request; timelines can be changed by written agreement for good cause (D.16) | Deemed withdrawn if deficiencies are not cured; a net metering or net billing request of 1 MW or smaller can be withdrawn after one year without a signed agreement, or one year after review ends without approval for parallel operation, unless it is still active or the delay is not the applicant's fault |
| Washington | Complete the application within 15 business days of an incomplete notice; the company may extend in writing | Clock starts when the application and fee are both received; delays from unforeseen circumstances, variance requests or incentive approvals require prompt notice only | Application expires if not completed; operate within one year of approval or it expires unless the company extends |
| Pennsylvania | Sign the agreement within 30 business days of receipt | A modification after a complete request needs a new request, except a minor equipment change agreed in writing (75.36(6)) | Deemed withdrawn if the agreement is not signed in 30 business days, unless an extension is requested; an extension may not be unreasonably denied |
| Maryland | Elect to continue within 10 business days if a minor system modification is needed; sign within 30 calendar days | A dispute suspends any deadline it directly affects (.13D) | Deemed withdrawn if the agreement is not signed in 30 calendar days, unless an extension is requested; an extension may not be unreasonably denied |
| Illinois | 10 business days to supply missing information; 30 business days to sign, with an extension of up to 15 that the first request cannot be denied | The 30-day informal dispute period, after which timeframes resume (466.130(b)) | Deemed withdrawn on a missed cure or signature deadline; before withdrawing an agreement the utility must give notice, and the customer has 5 business days to send it |
| Minnesota | 5 business days to supply missing items after the notice; 30 business days to sign or request an extension | Utility has 5 more business days to review the added material | Not in Sections 1 to 3; Section 1.6.3 sends disputes to section 5.3 |
The second is a request for more information. At the next tier up, Pennsylvania (75.38(c)(2)), Maryland (.10D) and Illinois (466.100(b)(4)) each say that the evaluation clock may be extended only by the delay needed to receive the information and that the utility may not restart the review or change the queue position. The Level 1 paragraphs in those three states contain no equivalent sentence, so a Level 1 information request is governed by the general deadlines.
The third is a change to the design. California allows one modification request per Fast Track request, to be processed in 10 business days, or 20 if a re-study is needed, and accepts like-for-like equipment replacements and size reductions inside limits that the Table F.1 lists; anything else needs a new request. Pennsylvania requires a new request for any change after a complete application except a minor equipment modification the utility agrees to in writing. A change of inverter model after filing falls under these provisions, so the installer should clear it with the utility before the equipment is swapped.
The fourth is a dispute, covered in the next section because it cuts both ways. The fifth is inactivity. California lets the utility withdraw a Fast Track request that has gone more than one year from the validity notice without a signed agreement, or one that has not been approved for parallel operation within a year of the end of review, unless the applicant shows the request is still active or the delay is not the applicant's fault. Washington's Tier 1 approval expires after a year without operation unless the company extends it. The guide to expanding an existing system covers the related case of a new application for added capacity.
When the deadline passes: the complaint ladder
The first step is to put the missed deadline in writing to a person the rule requires the utility to name. Washington requires a designated point of contact with a published telephone number and website, Pennsylvania a mailing address, an email address and a contact person in the tariff and on the website, Minnesota a DER interconnection coordinator, and California an ombudsman whose identity and contact information must be on the utility's website. Date the message, state the deadline the rule sets, count the business days, and attach the utility's last notice.
California's tariff is the most detailed about the next step. If the ombudsman cannot resolve a timeline dispute within 10 business days, the applicant may contact the Consumer Affairs Branch of the Commission, may ask by mutual agreement for mediation through the Commission's Administrative Law Judge Division, whose mediator then schedules a session within 10 business days of the request if resources allow, or may start the Section K process. A formal complaint at the Commission under Public Utilities Code section 1702 is open at any time. The Commission's complaint page says that an informal complaint is for the case where talking with the utility's customer service has not solved the problem. Section K starts with a written notice sent to the utility and copied to the Commission's Energy Division, and its expedited track asks the parties to meet within 15 business days of the notice.
| Jurisdiction | First step | Next step | Formal step |
|---|---|---|---|
| California, PG&E Rule 21 | The utility ombudsman the tariff requires; 10 business days to resolve (F.1.d, sheets 79 and 80) | CPUC Consumer Affairs Branch; or, by mutual agreement, mediation through the Commission's Administrative Law Judge Division; or the Section K process | Formal complaint under Public Utilities Code 1702 at any time; Section K starts with a written notice copied to the Commission's Energy Division |
| Washington | The utility's designated point of contact (480-108-030(2)) | Informal complaint to the commission under WAC 480-07-910 (480-108-005(5), 480-108-100) | Formal complaint under WAC 480-07-370 |
| Pennsylvania | The utility's designated contact (75.36(5)); parties attempt good-faith resolution (75.51(a)) | Written notice to the Commission and the other party to use its complaint procedures or an approved alternative (75.51(b)) | Commission complaint procedures; queue position is not affected (75.51(c)) |
| Maryland | Good-faith resolution between applicant and utility (.13A) | Procedures of COMAR 20.32.01; technical disputes go to the Commission's Engineering Division (.13B) | Hearing request under Public Utilities Article section 3-102 (.13E) |
| Illinois | Written notice to the utility; informal meeting within 10 business days (466.130(a),(b)) | Non-binding arbitration by an Ombudsman, limited to 60 days, costs shared equally (466.130(c)) | Formal complaint at the Commission before the 30-day informal period ends, so timeframes do not resume (466.130(b)) |
| Minnesota | The utility's DER interconnection coordinator, an information contact (MN DIP 1.3.1) | Section 1.6.3 refers to the dispute provisions in section 5.3, which is not part of Sections 1 to 3 | Not in Sections 1 to 3 |
Washington, Pennsylvania, Maryland and Illinois route the next step to the state commission. The Washington commission's page says it investigates informal complaints to see whether a company is following the rules, orders and tariffs, and that a formal complaint is a legal process that may be filed only to allege a violation of state law, a tariff, or a commission order or rule. Maryland sends technical disputes about the interconnection process to the Commission's Engineering Division, and Illinois gives a choice of Ombudsman arbitration by the American Arbitration Association, a designated Commission employee or a third party chosen by the parties, with the cost split equally.
A dispute can stop the clock you are complaining about. Maryland's rule on this is one sentence: "Any deadline imposed by the regulations in this chapter, which is directly affected by any issue in dispute, shall be suspended until resolution of the dispute." Illinois words it differently. The informal process runs for 30 days after the written notice, after which the dispute is deemed resolved and the timeframes for decisions resume unless a party seeks arbitration or files a formal complaint at the Commission before the 30 days end; resume implies they were paused. Pennsylvania and Maryland both say that pursuing dispute resolution does not cost the applicant its queue position. Whether a deadline that has already been missed counts as directly affected by the dispute over it is not spelled out in either text.
Customers of public utility districts, municipal utilities and special districts in Washington sit outside the commission's complaint route, as its page says, and the same question applies in the other states: find out which regulator, if any, oversees the utility before choosing a route. The net metering grandfathering guide explains why the date on the paperwork can matter beyond the wait, since some export tariffs key their terms to the application date and others to the day of permission to operate.
Papers to keep for a late-file complaint
- The date and time the utility acknowledged receipt, and the date of its completeness notice, since the review clock runs from one of them.
- The dates of every document you or the installer sent: application, inspection sign-off, certificate of completion, signed agreement.
- The rule section that sets the deadline, written next to the utility name, and the number of business days counted by weekday with holidays excluded.
- Every utility notice, with the names of people you spoke to and what each said about timing.
- Whether the application size is stated as inverter AC output, and the inverter model listed on it.
- The name and contact of the utility ombudsman, coordinator or designated contact the rule requires it to publish.
- Your installer's note of which utility decision the project is waiting for: application decision or permission to operate.
What a missed deadline does not change
In none of the six rulebooks does a lapsed deadline become an approval. Only Maryland's uses the words deemed approved, in two places, and neither is triggered by a missed deadline: a utility's inverter settings profile is deemed approved 90 days after filing (.06O(11)), and inverters and interface equipment that meet stated standards are deemed approved after January 1, 2024 (.07A and .07B). Deemed waiver exists for witness tests in Pennsylvania, Illinois and Minnesota, and Maryland's rule says a witness test not performed within 10 business days of the commissioning test is considered waived. Deemed withdrawal exists for customers who miss their own deadlines.
What the rules mostly attach to lateness is record keeping and notice. Pennsylvania requires each distribution company to keep records of the days taken to approve or deny requests and the number not processed within the subchapter's timelines, and to report them to the Commission within 30 calendar days of the close of each annualized period. Maryland requires utilities to retain, for seven years, a count of requests not processed within the chapter's deadlines, including a separate count for delays caused by a PJM market process study, and to file an annual report by April 1 that includes the number of requests not processed within the Level deadlines and the permission-to-operate deadlines. PG&E's tariff requires notice to the Commission when it misses the 30-day permission-to-operate target, and for requests that are placed in a queue it sets the queue date at the last day of the period in which a missed completeness notice was due; the sentence that assigns queue positions lists requests above 1 MW and requests outside net metering and net billing, so it is written for larger projects. A written complaint with dates adds a data point to counts that regulators in Pennsylvania and Maryland already collect.
The installer's contract is a separate document from the utility's rules, and its payment milestones are whatever the contract says. The quote red flags guide lists permission to operate among the milestones a payment schedule can be tied to, which keeps the last payment aligned with a system that can legally run. Ask in writing which of the two utility decisions a stalled project is waiting for, as the installation guide advises, before counting days against any of the rules above.
Fitting the wait into the project
The utility's maximum is one part of the wait. The whole sequence runs from design through the application, the permit and inspection, the certificate of completion and the final notice, and the PG&E and Maryland clocks for that final notice start at the customer's last document rather than at the date of the sale.
Two practical consequences follow from the structure. First, the order in which documents are sent matters: Rule 21 advises applicants whose projects use non-inverter or non-certified equipment, need a new service or need utility construction to submit the request without waiting for the final inspection clearance, and to submit at least six months before the planned commercial operation date. Second, the date the utility records as permission to operate may set later dates. The true-up bill guide explains how, under California's net billing tariff, the anniversary of that permission fixes the month the annual settlement lands, so a delay of weeks can move that month.
Interconnection deadline questions
How long does a utility have to approve a residential solar interconnection?
In the six jurisdictions checked, a complete small application has a written maximum of 20 to 35 business days to a decision: Maryland 20, Minnesota 20, Illinois 22, California and Pennsylvania 25, Washington 35. That is the review, not the whole wait; it excludes construction, inspection and the final permission to operate. Other states and other utilities have their own rules.
What is the difference between interconnection approval and permission to operate?
Approval of the application means the utility has accepted the design and will send or has sent an agreement. Permission to operate is the later written notice that lets the system run in parallel with the grid. The six rules tie operation to the second, and three put a day count on it: PG&E for net metering and net billing systems of 1 MW or smaller (30 business days after the complete request, signed agreement and inspection clearance, with a separate clause in Section F.5.b requiring written authorization within 5 business days of satisfactory compliance), Maryland (20 business days after acceptable documents) and Minnesota (3 business days after inspection or waiver).
Can I switch the system on if the utility misses its deadline?
None of the six rules says so. PG&E requires express written permission before parallel operation, Washington directs disconnection of an unapproved generating facility, and Minnesota and Illinois allow only short optional testing, up to two hours, before the final permission. Ask the utility in writing for the date, and use the complaint route in the table rather than operating without the notice.
Do the deadlines count weekends and holidays?
Where the term is defined, weekends do not count. Washington, PG&E and Illinois define business days as Monday through Friday excluding federal and state holidays. Pennsylvania, Maryland and Minnesota Sections 1 to 3 do not define the term, so ask the utility which calendar it uses.
Does my utility have to follow these rules?
Only if the rule covers it. Washington's chapter covers utilities under the state commission and not public utility districts or municipal utilities. Rule 21 here is PG&E's filed copy. Minnesota's text is Otter Tail Power's publication of the statewide process, and cooperatives and municipal utilities publish their own. Your utility's tariff and your state regulator's website say which rules apply.
Does a late approval affect my net metering or export rate?
It can, if the tariff keys its terms to a date in the paperwork. Some tariffs use the application date and others the date of permission to operate, so a delay can matter beyond the wait. The grandfathering and California net billing guides on this site explain which date to look for.
Start with the one number your own file needs: find the date the utility acknowledged your application as complete, add the review days from the table for your rule, and write the resulting date on the project file next to the installer's name. If that date has passed, send the written note described in the ladder before any phone call.
Sources and verification
- PG&E Electric Rule No. 21, Generating Facility Interconnections (tariff PDF; sheets cited carry effective dates of May 2, 2024 to August 29, 2025): Sections C (sheets 19, 32), D.1 (37), D.13 (44 to 46), F.5.b (126), D.16 (48), E.5 (70, 71), F.1.d (79, 80), F.2 (81, 82, 84), K (223 to 226); Table F.1. Checked November 3, 2026.
- WAC 480-108, Electric companies, interconnection with electric generators (Washington Legislature): Sections 005, 010, 020, 030, 040, 050, 100 and 110. Sections 005 to 050 and 110 were last amended by WSR 13-15-089, effective August 18, 2013; section 100 dates from WSR 07-20-059, effective October 28, 2007. Checked November 3, 2026.
- 52 Pa. Code Chapter 75, Alternative Energy Portfolio Standards (Pennsylvania Code and Bulletin): Sections 75.22, 75.34, 75.36, 75.37, 75.38, 75.51; the site states the Code reflects changes effective through 56 Pa.B. 6006 (September 5, 2026). Sections 75.22 and 75.51 were amended effective November 19, 2016; the chapter was adopted effective December 16, 2006, and the text shows no amendment note on sections 75.34 to 75.38. Checked November 3, 2026.
- COMAR 20.50.09, Small Generator Facility Interconnection Standards (Library of Maryland Regulations): Regulations .02, .06, .08, .09, .10, .13 and .14; chapter revised effective December 12, 2024, with .02B, .06N, .06S and .14C amended effective July 7, 2025. Checked November 3, 2026.
- 83 Ill. Adm. Code 466.90, Level 1 Expedited Review (Joint Committee on Administrative Rules): Amended at 46 Ill. Reg. 9666, effective May 26, 2022. The same host and amendment carry sections 466.20, 466.80, 466.100, 466.130, 466.140 and Appendix A. Checked November 3, 2026.
- 83 Ill. Adm. Code 466.130, Disputes (Joint Committee on Administrative Rules): Informal meeting, 30-day period, Ombudsman arbitration; Appendix A at https://www.ilga.gov/ftp/JCAR/AdminCode/083/08300466ZZ9996AR.html for the witness-test terms. Checked November 3, 2026.
- Minnesota Distributed Energy Resource Interconnection Process (MN DIP), Sections 1 to 3, as published by Otter Tail Power Company: Section 2 (Simplified Process); Section 1 at https://www.otpco.com/media/00jj5jda/section_1.pdf and Section 3 at https://www.otpco.com/media/gq2ntx2h/section_3.pdf. The files carry no edition date. Checked November 3, 2026.
- Minnesota Public Utilities Commission staff, Minnesota Interconnection Progress (May 19, 2025 webinar slides, hosted by Lawrence Berkeley National Laboratory): Slide 9 process-track estimates; the slides state that they are the views of the presenters and not the Commission. Checked November 3, 2026.
- Washington Utilities and Transportation Commission, File a Complaint: Informal and formal complaint steps; public utility districts and municipal utilities contact the utility directly. Checked November 3, 2026.
- California Public Utilities Commission, File a Complaint: Utility complaint and formal complaint descriptions. Checked November 3, 2026.
Six rulebooks are in the tables: PG&E's Electric Rule 21, WAC 480-108, 52 Pa. Code chapter 75, COMAR 20.50.09, 83 Ill. Adm. Code 466 and Sections 1 to 3 of the Minnesota process as published by Otter Tail Power. Other states, other California utilities, and Minnesota's cooperative and municipal utilities have their own texts, and New Jersey is not in the table. California's initial-review screens (Section G.1), the non-export tracks in Maryland and Pennsylvania, Minnesota's dispute section (5.3) and glossary, and Maryland's .08A timing relative to the completeness notice are not tabulated. Each row is the text as printed on November 3, 2026, with the last amendment shown in the source note; a pending rulemaking after that date is not reflected. The rows describe the shortest track for a certified, inverter-based home system with no utility construction, and tariffs, forms and utility practice can add steps. Counts are the maximums the rules give the utility and exclude customer time. Rule 21 does not say whether the five-business-day authorization in F.5.b falls inside or after the 30 business days in D.13.b, so both totals are shown. Nothing here is legal advice, a prediction for a particular utility, or evidence of how fast any utility actually works, and the utility's own tariff and your state regulator outrank this guide.