Pricing the quote and the contract

Can you install solar panels yourself? Owner permit, electrician and utility rules in seven states

Seven state laws checked for this article, in Washington, Oregon, Florida, Texas, Minnesota, Wisconsin and Arizona, let an owner who lives in the house install solar on it without the trade license the state's law would otherwise require. The license is the only thing they excuse. The permit, the code inspection and the utility's written approval to run in parallel with the grid still stand in front of the switch, and most of the seven take the exemption away when the work is done for a sale or a rental.

Money is the reason most people ask, so the figure to hold is the Department of Energy's Q1 2025 residential benchmark: $2.95 per watt DC for an 8 kW system, $23,600 in 2024 dollars. Splitting that price along the lines of DOE's own cost model, $10,600 is hardware with its distributor markup and sales tax, $2,447 is permitting and electrical design, $3,273 is crew and office time that becomes the owner's own hours, and $7,247 is marketing, management and installer profit that no longer appears on any invoice. None of those four figures is a promise about what a self-installed system costs; the hardware alone is priced in the model at what an installer pays, not what a household pays.

Owner-installer rules in seven states, from the statutes

Each of these licensing laws carries a list of people who do not need a license, and an owner working on their own home is on it in all seven. The differences sit in the conditions: how long you must keep the house, whether a city can take the exemption back, whether the dwelling needs its own service, and what the utility's rule requires before it lets the system export. The table quotes the operative condition of each law rather than a summary of it, because the condition is where a DIY project goes wrong.

Owner-occupant electrical work and the step before power-up, by state. Statute and rule text from each state's official legislature or rules site, checked October 31, 2026. Utility rules apply to the utilities each rule names.
StateWho may do the work without a licenseWhat ends the exemptionBefore the utility lets it run
WashingtonRCW 19.28.261: a person doing electrical work at their own residence or on other property they own needs no license and no certified electricianConstruction of a new building intended for rent, sale or lease, or property offered for sale within 12 months of obtaining it (an affidavit route exists for an owner who will live in one unit of a new building of up to four units)WAC 480-108-050: a certificate of completion showing permits, code compliance and the electrical inspector's approval, accepted in writing by the utility; RCW 19.28.101 lets the utility connect once approval shows on the permit
OregonORS 479.540(1): no license for an electrical installation on residential or farm property owned by the person or a member of their immediate familyProperty intended for sale, exchange, lease or rent; the work still has to meet ORS chapter 455, chapter 479 and their rulesORS 479.570: a seller of electricity may not energize an installation until an authorized inspector approves it, unless a licensed supervising electrician makes a written request with the permit attached
Floridas. 489.503(6)(a): an owner may apply for the permit, supervise and do the work on a single-family or duplex residence for their own use and occupancyBuilding for sale or lease; the owner must personally appear and sign the permit application; sale or lease of more than one such structure within 1 year is prima facie evidence of a sale purpose; anyone the owner hires to act as a contractor is not exemptRule 25-6.065 (investor-owned utilities): local code officials inspect and approve before parallel operation; the customer gives 10 days' notice before the in-service date; no liability insurance may be required for Tier 1 (10 kW or less)
TexasOccupations Code s. 1305.003(a)(6): the electrician licensing chapter does not apply to work in or on a dwelling by a person who owns and resides in itApplies only to work not specifically regulated by a municipal ordinance, so a city electrical ordinance can bring the work back under local rules16 TAC s. 25.211 (read) covers pre-interconnection studies, their fees, and disconnection and reconnection; ask the utility what its application requires before operation
Minnesotas. 326B.33, subd. 21(f): an individual who physically performs the work on a dwelling they own and occupy, or will occupy on completion, needs no licenseThe dwelling must have its own electrical utility service, not shared with another dwellings. 326B.36, subd. 4: the owner making the installation submits the request for inspection, with fees, at or before the start of work; the utility rule was not read
Wisconsins. 101.862(4)(a): a residential property owner may install, repair or maintain wiring on premises they own and occupy as a residenceA local ordinance that requires a state license or registrationPSC 119.04: after notice that the installation meets all codes, including state and local inspections, the utility has 10 working days for a Category 1 system (export of 20 kW or less) to witness tests, run its own check, or waive in writing
ArizonaA.R.S. 32-1121(A)(5): owners who improve their own property and do the work themselves, with their own employees or with licensed contractors, are exempt from contractor licensingThe structure must be for the owner's sole occupancy and not for sale or rent; a sale or rental offer within one year of completion is prima facie evidence of a sale purposeThe Arizona Corporation Commission's interconnection rule could not be read for this table; the serving utility's tariff sets the steps

Two patterns run through the table. The first is ownership and use. Every exemption is written around the owner, five of the seven (Florida, Texas, Minnesota, Wisconsin and Arizona) also require that the owner occupy the home, and four attach a sale or rental test: a 12-month window in Washington, a one-year presumption in Florida and Arizona, and an intent test in Oregon. Texas and Wisconsin hand the question partly to local government, so the same owner can be exempt in one city and not in the next. Minnesota adds a physical test that has nothing to do with intent: a duplex or an accessory dwelling sharing one utility service with the main house is outside the exemption.

The second pattern is that the utility column never mentions licenses at all. Washington, Oregon, Florida and Wisconsin each tie the utility's go-ahead to an inspection by the authority having jurisdiction, and Oregon is explicit that the exception that can apply to a house system belongs to a licensed supervising electrician. The utility rules apply to the utilities they name: Washington's chapter to companies regulated by its utilities commission, Florida's rule to investor-owned utilities, Wisconsin's chapter to public utilities. Municipal utilities and cooperatives in those states set their own interconnection terms, so their application form is the document to read.

What the owner exemption does not waive

Oregon says it in the statute itself. The owner's license exemption in ORS 479.540 does not exempt the work from having to comply with the requirements of ORS chapter 455 and chapter 479, which is where the permit and inspection obligations live. Washington's statute does the same from the other side: RCW 19.28.261 says nothing in its licensing sections derogates from a city's valid electrical code, and RCW 19.28.101 has the state's inspectors inspect all wiring the chapter covers, with permits issued on payment of the fee. A homeowner who is not required to hold a license is still required to build to the code and to show the inspector that they did.

Minnesota puts the owner directly into the inspection procedure. Section 326B.36, subdivision 4 lists "the contractor, installer, special electrician, or owner making the installation" as the person who must submit the request for inspection at or before the start of any installation the commissioner inspects, together with the handling and inspection fees. Florida's exemption is conditioned on the permit: the owner must personally appear and sign the building permit application, satisfy any local requirement that they understand their obligations under the disclosure statement the statute prints, and, if the conditions are broken, the local permitting agency must withhold final approval, revoke the permit or pursue an unlicensed-activity action.

None of that is unusual. What it means in practice is that a self-installed system goes through the same plan review, the same rough and final inspections and the same correction notices as an installer's. The difference is who answers them. When an inspector writes a correction for an installer, the installer's crew returns; when the owner is the permit holder, the correction is the owner's to fix, often after a second trip onto the roof and a re-inspection booking.

Who signs the permit application, and the automated route that is not open to owners

The person who signs the permit is the person the jurisdiction holds responsible for the work, which is why owner-builder rules attach to the application itself. Florida is the clearest example: the owner must appear in person and sign, and the statute prints a disclosure statement telling them they may not hire an unlicensed person as their electrical contractor and that they are responsible for making sure anyone they employ holds the licenses state and local law require.

Arizona's exemption, unlike Florida's and Washington's, names the owner's own employees and duly licensed contractors as acceptable helpers, but only within its owner-occupancy condition. Read the clause on helpers before inviting one onto the roof.

Many cities now issue residential solar permits through SolarAPP+, the automated plan-review platform. Its own site describes it as "available to licensed contractors", which places the instant-permit route on the contractor's side of the counter. An owner who pulls their own permit should expect the jurisdiction's ordinary plan review, with its own submission requirements and turnaround, and should ask the permit office whether an owner-builder application uses a separate form. The fee schedule is a separate question, priced line by line in the solar permit cost guide.

The exemption does not stretch to paid helpers

Paying a friend or an unlicensed handyman to do the wiring under the owner's exemption. The exemption belongs to the owner personally. Florida's paragraph (6)(c) excludes anyone the owner employs who acts in the capacity of a contractor, and its disclosure statement says the owner may not hire an unlicensed person as their electrical contractor; Washington's clause covers the owner on their own property and a business's regularly employed staff, not paid help; Minnesota's covers the individual who physically performs the work. Unpaid help from family is a different question in each state, and Oregon's exemption is the one that names immediate family. Hire a licensed electrician for the part you are not doing yourself.

When the exemption runs out: resale windows, rentals and shared services

Owner exemptions exist so people can work on their own homes. They are written to stop the same exemption becoming a way to build or flip houses without a license, and the guardrails are specific. Washington removes the exemption for property offered for sale within 12 months of obtaining it and for new buildings meant for rent, sale or lease. Florida treats the sale or lease of more than one such structure within a year of completion as prima facie evidence that the work was done for sale. Arizona uses a one-year presumption from completion or certificate of occupancy. Oregon removes the exemption when the property is intended for sale, exchange, lease or rent, and limits a landlord to maintenance-type work on existing installations.

For a solar owner, the practical consequence is timing. Someone who plans to sell within a year or so should treat an owner-installed system as a disclosure item and a possible enforcement question, not a selling point, and should check whether the work was permitted and finaled before listing. A rental is plainer still: in Oregon, new electrical installations or substantial alterations on a residence that is for rent are outside the owner exemption, and a rooftop array with its wiring is a new installation. The resale side of a solar sale is covered in what moving does to payback.

Texas and Wisconsin move the line to local government. The Texas exemption covers only work "not specifically regulated by a municipal ordinance", and Wisconsin's applies unless a license or registration is required by local ordinance. In both states, the city's electrical ordinance, not the state statute, decides whether the owner may do the work at that address. Minnesota's condition is physical: the dwelling must have a separate electrical utility service not shared with any other dwelling, so the owner of a house and a garage apartment on one meter is outside the exemption for that service.

The utility's sign-off is its own gate

Passing the electrical inspection does not by itself let a grid-tied system run. Washington's interconnection rule says the process is complete, and the generating facility may begin operating, only when the customer and the utility have executed an interconnection agreement and the utility has approved in writing a certificate of completion showing the required electrical and building permits, compliance with the technical rules, and inspection and approval by the electrical inspector having jurisdiction. If the utility requires it, its own representative witnesses the system's operation as well.

Oregon goes further and puts the duty on the utility: a person who sells electricity may not energize an installation unless it has first been approved by an authorized inspector. The exception that can apply to a house system, a written request to energize from a licensed supervising electrician with the permit attached, is not available to an unlicensed owner, which makes the inspection the owner's only path to power. Florida's rule writes the same sequence into the standard agreement for investor-owned utilities: the system must be inspected and approved by local code officials before it operates in parallel with the utility, and the customer must give the utility 10 days' notice before first placing the equipment in service, with the utility entitled to have staff present.

Wisconsin's rule sets the clock from the other side. Once the applicant notifies the utility that the installation is complete and meets all applicable codes, including any necessary state and local inspections, the utility has 10 working days for a Category 1 or 2 system to witness commissioning tests, run an unintentional islanding test or verify protective settings, or waive its right to witness in writing. A Category 1 system is one exporting 20 kW or less, which covers the 8 kW reference system and almost every household roof.

Two details in these rules are friendlier to small owner systems than people expect. Florida's rule forbids investor-owned utilities from requiring liability insurance for Tier 1 systems, which are 10 kW or less, though the agreement may recommend it. Wisconsin's rule also sets review clocks for the application itself, 10 working days for a Category 1 engineering review where one is needed. Neither detail removes the application, and filing it before equipment is bought lets the utility flag a study or an upgrade while the plan can still change. How the export credit is then calculated is a separate tariff question, set out in the net metering explainer.

The $23,600 Q1 2025 benchmark, split by what a DIY installer still pays

DOE publishes the cost model behind its benchmark as a set of files, and the residential file lists every line of the 8 kW reference system: twenty 400 watt modules on rails and flashed roof mounts, a 350 watt microinverter under each module, a combiner box, breaker boxes and a system monitor, the crew's field labor, the office's work, and the installer's overhead and profit. Pricing each line at the model's market-price inputs and grouping them by what changes when the owner does the work gives the split below. The lines sum to $23,567; the published headline is $2.95 per watt, or $23,600, and the $33 difference is rounding in the headline figure.

DOE Q1 2025 residential benchmark, 8 kW PV-only, modeled market price, 2024 dollars. Line values worked out from the inputs and factors in RPV 2025Q1.txt, the residential file in DOE's cost model release (file dated November 13, 2025); fixed inputs are printed in the file as given. Read October 31, 2026.
Model lineWhat the file says it covers8 kW dollarsWith an owner install
Modules, microinverters, racking and electrical hardwareEquipment as delivered to the installer, priced with the import tariffs the model applies$9,636Still paid in cash, at whatever price a household can buy at
Distributor markup and sales tax5 percent of hardware value each$964Still paid in cash
PermitsPreparation cost and the jurisdictional fee, nearly independent of size$2,152Fee still paid in cash; preparation becomes the owner's time
Electrical designDesign time, nearly independent of size$295Owner's time, or a paid plan set
Site assessmentAssessment time, independent of size$1,067Owner's time, or a paid engineer's letter where the roof needs one
Field laborRacking and modules, inverter mounting and wiring, site management, and on-site labor to support the permit inspection$1,955Owner's time
LogisticsInventory management and transport arrangements$251Owner's time, plus any delivery charge
Customer acquisitionSales and marketing cost to win one customer$3,472Leaves the invoice
Management and profitInstaller management salaries spread over 1,000 kW a year, and a 15 percent developer profit$3,775Leaves the invoice
Total of the linesSums to the $2.95 per watt headline after rounding$23,567

Grouped, the four outcomes are $10,600 still paid in cash for equipment, markup and tax; $2,447 for permitting and design, of which the jurisdiction's fee is cash and the rest is work someone must do; $3,273 of site assessment, field labor and logistics that becomes the owner's hours; and $7,247 of marketing, management and profit that a self-installer does not pay at all. The four add to $23,567. The $7,247 is the part of a professional installation that pays for the installer's business, not a measure of the installer's skill or of what the owner would lose by doing the work badly.

The hardware line is the one most likely to mislead. DOE models equipment at the price a small regional installer pays, delivered, with a 5 percent distributor markup on top; a household buying one system's worth of panels, inverters and racking does not get an installer's price and usually pays freight and handling on a single order. The file also does not split the $2,152 permit line between the jurisdiction's fee and the paperwork, so the cash part of that line depends on the city. The model's fieldwork note excludes two things that often appear on real jobs, an electrical service upgrade and roof repair, both of which an owner install still needs when the house needs them; the panel case is worked through in the main panel upgrade guide. How the fixed lines shift with system size is shown in the cost-per-watt guide.

The crew hours inside the field-labor line

The model prices field labor from stated hours, which gives an owner a rough sense of the work being taken on. Racking installation and module mounting are modeled at 0.3 hours per square meter of modules; the twenty-module array covers about 39.2 square meters, so that is about 11.8 crew hours, priced at $762. Inverter mounting, wiring, grounding, testing and commissioning are modeled at 2 hours per kW of inverter capacity; with 7.0 kW of microinverters that is about 14.0 hours, priced at $765. On-site management adds about 1.5 hours and $182, and on-site support for the permit inspection is a fixed $246.

That is about 27 hours for an experienced crew with the right equipment, staging and fall protection, working a design it has installed many times. A first-time owner should expect more, and the hours land in an awkward order: roof attachments and flashing come first and are the hardest to redo, while the electrical connection at the panel, the part with the most code rules attached, comes last. The $765 electrical labor line is also the most useful benchmark for one common middle path, hiring a licensed electrician only for the electrical half, which is the next section's subject.

None of these hours includes the time spent on the permit set, the utility application or the inspections themselves beyond the model's fixed lines. The design line is $295 because an installer's designer reuses standard drawings; an owner preparing a first plan set, a one-line diagram and the structural information the permit office asks for will spend far longer, or will buy that work from someone who has done it before.

Splitting the job: owner on the roof, licensed electrician at the panel

A common compromise is for the owner to do the racking and module mounting and to hire a licensed electrician for the inverter wiring, the disconnect, the connection at the service panel and the inspection. The laws in the table make that arrangement straightforward in principle, because the owner is exempt and the electrician is licensed, but the permit has to match it. Ask the permit office whether the electrical portion must be on the electrician's own permit, whether the owner can hold a building permit for the structural work alongside it, and who requests each inspection.

Oregon shows why the split matters at the end of the job. An installation can be energized before the final inspection in that state only on a written request from a licensed supervising electrician with the permit attached, and it must still receive final inspection afterward. An owner working alone waits for the inspector; a project with a licensed supervising electrician on the electrical permit has that additional route available, subject to the electrician's willingness to sign for the work.

In dollar terms, the model's split puts the roof half at $762 of mounting labor and the electrical half at $765 of wiring, grounding, testing and commissioning, with another $246 of inspection support. An electrician hired for one small job does not price at a crew's per-hour rate inside a volume business, so the model figure is a floor for comparison, not a quote to expect. Before hiring, the same license lookup that applies to a full installer applies to the electrician; the installer license checks show how each state's record is searched.

Warranty, insurance and what an owner install leaves uncovered

Installers commonly offer a workmanship warranty on the installation itself, written into the contract and separate from the manufacturers' product warranties. An owner install has no workmanship warranty by definition: if a flashing leaks or a connector fails because of how it was assembled, the owner is both the installer and the person paying for the repair. Whether a manufacturer's product warranty depends on who installed the equipment is set by each manufacturer's warranty terms, which differ, so read the terms for the specific modules and inverters before buying rather than after.

Inverter makers' service documents show where the line between equipment fault and installation fault falls. SMA's technical information on insulation errors says the corrective measures it describes may only be carried out by qualified persons, and that damage caused by a ground fault during operation is not considered a fault of the inverter and is therefore not covered by the warranty, because the inverter meets the standard requirements. SMA names defective cable insulation and plug connections among the causes of insulation errors, and that is the wiring an owner does. What those faults look like on the inverter screen is covered in the isolation fault guide.

Insurance raises a separate question. Florida's rule bars investor-owned utilities from requiring liability insurance for systems of 10 kW or less, but a homeowner's own policy is a different contract, and an insurer may ask whether the system was permitted and inspected. The home insurance side, including how rooftop systems are scheduled, is set out in the solar homeowners insurance guide. Roof warranties are the other contract to read before drilling: a roofing manufacturer or contractor warranty may set conditions on penetrations, and the roof warranty guide lists what to look for.

The paper trail for an owner-built array

  • The state's owner exemption clause, read in full, including its sale, rental and occupancy conditions.
  • Whether your city or county has an electrical ordinance that overrides the state exemption, which matters most in Texas and Wisconsin.
  • Whether the house has its own utility service, if you are in Minnesota or have an accessory unit on the same meter.
  • The permit office's owner-builder application, its plan-set requirements and whether the electrical work needs a separate permit.
  • The utility's interconnection application, filed and approved before equipment goes on the roof, with the size category it places your system in.
  • The manufacturers' warranty terms for the exact modules and inverters, read for any installer condition before purchase.
  • Your homeowners insurer's questions about a self-installed system, answered in writing.
  • A realistic hour count for your roof, starting from the model's 27 crew hours and adding time for a first install.

Projects with different rules: plug-in kits, off-grid cabins and non-export systems

Three kinds of project often get lumped in with DIY rooftop solar and follow different rules. Plug-in or balcony solar, a small kit that plugs into an ordinary outlet, is addressed by a handful of state laws written for it specifically, which are compared in the plug-in solar state guide. A permanently wired rooftop array is not a plug-in kit, whatever the size of the kit it came in.

An off-grid system on a cabin or outbuilding never connects to a utility, so the utility column of the table drops away, but the owner exemptions above still decide who may do the wiring, because they are about electrical work, not about whether the work connects to the grid, and the permit office still sets the permit rules. Off-grid sizing and battery costs are priced in the off-grid solar cost guide. A grid-tied system configured never to export sits in between; whether a utility still requires an application for it is set by the utility's own rules, and the non-export solar guide covers that case.

Batteries add their own layer. A home battery is electrical work under the same exemptions, but its location, capacity limits and protection requirements come from the residential code, and an owner install has to meet them as fully as a contractor's; the rules are laid out in the battery location guide. The DOE model's battery case also shows how much work a battery adds: about 16 hours of installation labor per unit, on top of the PV figures above.

Pricing an owner install against the line

Because the hardware price is the biggest unknown, the cleanest comparison is a range. The table below keeps every non-hardware line from the DOE model at its modeled value and varies only what the household pays for equipment, markup and tax relative to the model's installer price. The percentages are illustration inputs, not market data; replace them with the totals from real retail quotes for the same equipment.

Illustration: cash outlay for an owner-installed 8 kW system, using DOE Q1 2025 model lines (2024 dollars). Hardware, markup and tax of $10,600 are scaled by the stated percentage; permits and design are held at $2,447. Owner hours, tools, re-inspections and lost warranty coverage are not priced.
Household hardware price vs modelHardware, markup and taxPlus permits and designCash outlayGap to the $23,600 line
Same as the model$10,600$2,447$13,047$10,553
20 percent above the model$12,720$2,447$15,167$8,433
40 percent above the model$14,840$2,447$17,287$6,313

The gap column is not a return. It is what the owner stops paying an installer, and against it sit at least 27 hours of skilled work at the model's crew pace, the tools and safety equipment to do it, the cost of any correction an inspector writes, and the absence of a workmanship warranty. It also assumes the permit line's preparation work is bought rather than done, which is why the full $2,447 stays in the cash column. If those costs or the hours outweigh the gap for your roof, an installer's price near the benchmark is the cheaper option, and the quote comparison tool tests a quote against the same line.

An Oregon owner prices the reference system both ways

An owner in Oregon, living in a single-family house with its own service, plans the DOE reference system: twenty 400 watt modules on a composition shingle roof, one microinverter per module, 8 kW DC and 7.0 kW AC. The house is not for sale or rent, so ORS 479.540 exempts the owner from the electrical license, but the work must meet chapter 455 and 479 requirements, so the owner applies for the electrical permit and books inspections. The utility may not energize the system until an authorized inspector approves it, because there is no licensed supervising electrician to request energizing.

On the money side, the owner prices equipment at retail and finds the hardware, markup and tax total 20 percent above the model's $10,600, or $12,720. Holding permits and design at $2,447 gives a cash outlay of $15,167. Against the benchmark's $23,600, the difference is $8,433, before roughly 27 crew hours of work at a professional pace (11.8 on the roof, 14.0 on the electrical side, 1.5 managing the site), plus inspection visits.

The owner then prices the split option: an electrician for the electrical half. The model's own figure for that half is $765 of wiring labor plus $246 of inspection support, $1,011, and a one-off electrician's quote will sit above that floor. If the quote came in at, say, $2,500 (an illustration figure), the cash outlay would rise to $17,667 and the gap to the benchmark would narrow to $5,933, with the roof work still the owner's and the electrical work carrying a licensed professional's name and, usually, their workmanship terms.

DIY solar permit and license questions

Is it legal to install solar panels yourself?

In Washington, Oregon, Florida, Texas, Minnesota, Wisconsin and Arizona, an owner who lives in the house may do the work without the trade license otherwise required, subject to conditions in each statute: no building for sale or rent, and in Texas and Wisconsin no local ordinance requiring a license. A permit, the code inspection and the utility's approval still apply wherever they normally would.

Do I need a licensed electrician to connect solar panels to my house?

Not under the owner exemptions in the states tabled here, as long as you meet their conditions. The exemption covers the license only. The connection still has to be permitted, built to the electrical code and approved by the inspector, and in Oregon the utility may not energize it without that approval unless a licensed supervising electrician requests it.

Can a homeowner pull their own solar permit?

Florida and Minnesota write the owner into the permit and inspection process by name: Florida requires the owner to appear in person and sign the application, and Minnesota lets the owner submit the request for inspection. Elsewhere the permit office's own form governs. SolarAPP+, the automated permitting platform many cities use, describes itself as available to licensed contractors, so an owner's application usually goes through the city's ordinary plan review instead.

How much of the cost of solar is installation labor?

In the DOE Q1 2025 model for an 8 kW system priced at $23,600, field labor is $1,955, including $762 for racking and modules and $765 for electrical work. Marketing, management and installer profit add $7,247, and site assessment and logistics $1,318. Hardware with markup and tax is $10,600, at installer prices.

Will the utility connect a system I installed myself?

The utility rules read here do not ask who installed the system. They ask for an approved interconnection application, an agreement, and proof that the authority having jurisdiction inspected and approved the work. Washington's rule requires a certificate of completion the utility approves in writing, and Wisconsin's gives the utility 10 working days for a small system after notice of completion.

Does installing solar myself void the warranty?

There is no workmanship warranty on an owner install, because there is no installer. Product warranty conditions are set by each manufacturer's terms, so read them for the exact equipment. SMA's guidance, for example, says ground-fault damage during operation is not a fault of the inverter and is not covered, and those faults often start in the wiring.

The legal part of a DIY solar project is short: one exemption clause, a few conditions, and two approvals that every system needs regardless of who builds it. The money part is longer, because the installer share that disappears is real but is paid back in hours, risk and a missing workmanship warranty. Put the state clause, the utility's application and a retail hardware total side by side, and the answer for a given roof is usually clear before anything is bolted down.

Sources and verification

State rows come only from statutes and rules read on official state sites. Utah's code page did not render its text and the Arizona Corporation Commission's rule could not be read, so Utah is omitted and Arizona's utility cell is blank of rule text. No city or county ordinance, utility tariff or interconnection form was read; municipal and cooperative utilities set their own terms. The SolarAPP+ installer terms page was not read beyond the home page. DOE category dollars are re-derived from the model's input file and sum to $23,567 against the $23,600 headline; the module line alone fell outside the file's printed module range in that re-derivation, so hardware is shown as one total. Hardware is priced at installer cost, not retail. The 20 and 40 percent hardware markups and the $2,500 electrician figure are illustration inputs. This is not legal advice; the permit office and utility decide each case.