Iowa solar billing in 2027: what Code 476.49 changes on July 1, what stays fixed for 20 years, and an 8 kW month billed two ways
Iowa's solar billing rules do not switch off on July 1, 2027. After that date a utility may petition the Iowa Utilities Commission for a value-of-solar proceeding, and the Commission must open one earlier if statewide distributed generation reaches 5 percent of peak demand. The Commission's own table puts statewide penetration at 3.90 percent for 2025, and for a facility already interconnected the statute pays exports at the retail volumetric rate for a 20-year term.
Section 476.49 of the Iowa Code, enacted as Senate File 583 in 2020, lets a rate-regulated utility choose between two methods: net billing, which nets exported kilowatt-hours against imported ones over a monthly interval, and inflow-outflow billing, which meters by the hour or finer and credits exports in dollars. Until a value-of-solar rate exists, that dollar credit equals the retail volumetric rate. On the 8 kW roof worked below, a July month that costs $118.00 without solar costs $10.00 under either method, and the two part ways only at the year-end settlement: a leftover 1,080 kWh earns a $16.20 customer share under net billing's cash-out (at an illustrative 3-cent avoided cost), while the same surplus becomes $129.60 of forfeited dollar credits under inflow-outflow billing.
The word net billing means something different in Iowa's statute than it does in California or Utah, where it names an export rate below retail. And the statute holds three separate 20-year clauses with different triggers, which are easy to merge into one promise: one holds a formula, one fixes a number, and one keeps a tariff available after a 10 percent review.
Who section 476.49 binds
Senate File 583 passed the Senate 28 to 19 on March 18, 2019, and the House sent it back to its Commerce Committee on April 27, 2019. On March 3, 2020 the House adopted the committee amendment, H-8033 as amended, and passed the bill 98 to 0. The Senate concurred 48 to 0 on March 4, and the Governor signed it on March 12, 2020 as chapter 1004 of the 2020 Acts, effective July 1, 2020. The enrolled act wrote the new section as 476.49 and spoke of the Iowa Utilities Board; the 2026 Code calls the same body the commission.
The duty falls on one class of utility. Subsection 1, paragraph d, defines an electric utility for this section as "a public utility that furnishes electricity to the public for compensation that is required to be rate-regulated under this chapter." Section 476.1A, subsection 1, then provides that "Electric public utilities having fewer than ten thousand customers and electric cooperative corporations and associations are not subject to the regulation authority of the commission, except for regulatory action pertaining to all of the following," which is five matters: support fees, safety and engineering standards, assigned service areas, railroad crossings, and alternate energy purchase program plans under section 476.47. Section 476.1B, subsection 1, gives municipally owned utilities the same exemption with a similar list. Neither section's list of retained matters, nor the list of additional sections in its subsection 2, names section 476.49. Subsection 4 of section 476.1A lets a cooperative elect to have its rates regulated by the commission, and a cooperative that makes that election would then appear to fall within the definition in paragraph d. The Commission's distributed generation page names Interstate Power and Light and MidAmerican Energy as the utilities required to file tariffs under the statute. A customer of a cooperative or a city utility is governed by the policy that board or council has adopted, not by the tariff language discussed here.
The Commission's own rule points the same way. Rule 199-15.10(3), last amended effective July 16, 2025, provides: "Each utility shall offer to operate in parallel through either net metering (with a single meter monitoring only the net amount of electricity sold or purchased) or inflow-outflow billing with an AEP facility, provided that the facility complies with any applicable standards established in accordance with these rules." A second paragraph adds that, by choice of the facility, the utility and the facility may instead operate in a purchase and sale arrangement under which anything the facility delivers is sold to the utility at the tariffed rate. That alternative is a different product, priced differently from either billing method.
| Condition | Statutory wording | What it means for an 8 kW roof |
|---|---|---|
| Location | Located behind a customer's electricity meter | A rooftop array serving the house qualifies; a separate generating site selling to the grid does not |
| Connection | Interconnected to the electric utility distribution system | The utility's interconnection approval comes first |
| Size | Aggregate nameplate capacity less than or equal to one megawatt alternating current | 8 kW sits far under the ceiling |
| Output ceiling | Capability to produce no more than one hundred ten percent of the customer's annual electricity usage | For a home using 10,800 kWh a year, capability up to 11,880 kWh |
| Purpose | Generating capacity and associated energy intended to serve only the on-site electric requirements of the customer | Sizing to the house, not to export |
| Election | Elects a billing method pursuant to subsection 3 | The customer chooses from the methods the utility has filed |
The 110 percent ceiling is a capability test, and the statute does not say how capability is measured. MidAmerican's Rate IO answers for solar: the utility estimates expected output with the National Renewable Energy Laboratory's PVWatts Calculator and compares it with the customer's average annual use over three years of data where available. Its own worked example takes a home using 9,451 kWh a year with a 12 kW AC array estimated at 18,133 kWh, which is 192 percent of the load. The share of exports that qualifies for the billing arrangement is then 110 percent of 9,451, or 10,396 kWh, divided by 18,133, which is 57 percent, and the other 43 percent is bought under Rate AEP or Rate QF instead. An 8 kW system sized to a normal bill sits well under the ceiling, so the ceiling matters mostly to someone adding a large array to a small load.
Net billing and inflow-outflow, side by side
Subsection 3 requires an electric utility to "file either a net billing or an inflow-outflow billing tariff with the commission." Paragraph a describes the first method and paragraph b the second, and the definitions in subsection 1 attach an interval to each: net billing uses a net metering interval "equal to a monthly billing period," and inflow-outflow billing a net metering interval "measured hourly or subhourly." Both methods start from the same charge: the customer "pays all applicable charges, including applicable rider charges approved by the commission and applied to non-net metering customers, for the electricity delivered" over the interval. They differ in how the exports come back.
| Feature | Net billing (3(a)) | Inflow-outflow billing (3(b)) |
|---|---|---|
| Interval | A monthly billing period | Hourly or subhourly; the utility selects the interval |
| Credit unit | Kilowatt-hours for energy exported | Dollars at the outflow purchase rate for energy exported |
| What credits offset | Kilowatt-hours in future billing periods, including applicable volumetric rider charges | Applicable volumetric charges, including rider charges, billed on a kilowatt-hour basis |
| Price of an exported kWh | The price of an imported kWh, because kilowatt-hours offset kilowatt-hours | The outflow purchase rate: the applicable retail volumetric rate until a value-of-solar rate is approved |
| Leftover at year end | Excess kWh at the end of a twelve-month period are cashed out at the utility's avoided cost rate, with the funds divided evenly between the customer and the utility's low-income home energy assistance program | Outflow purchase credits remaining at the end of an annual period are forfeited to the rider the utility uses to recover them |
| Year-end date | January or April, chosen at interconnection | January or April, chosen at interconnection |
| Demand limits | Not limited in any way based on a customer's peak demand | Not limited in any way based on a customer's peak demand |
| Extra fees | None that are not charged to customers in the same rate class that are not net billing customers | None that are not charged to customers in the same rate class that are not inflow-outflow customers |
On the statute's wording, net billing is the richer of the two on exported energy: a kilowatt-hour sent out cancels a kilowatt-hour taken in, and a leftover balance at the settlement date pays something instead of being forfeited. Inflow-outflow billing matches it on a monthly bill only while the outflow purchase rate equals the retail volumetric rate, and subsection 4 describes how that equality can end. Until it does, the choice between the methods rarely shows up on a single month's bill.
That is a different meaning of net billing from the one used on the net metering explainer, which defines net billing as retail pricing for imports and a separate, lower export rate. Under that definition Iowa's inflow-outflow billing is the structure that can turn into net billing once a value-of-solar rate lowers the outflow purchase rate, while Iowa's statutory net billing is closer to monthly net metering with a cash-out. Utah's Schedule 137 and California's tariff, covered in the Utah export credit guide and the California net billing guide, use the term in the lower-export-rate sense. When a quote or a website says Iowa has net billing, ask which meaning it intends and read the tariff's credit line instead.
Credits in both methods offset charges that scale with usage and nothing else. The statute says dollar credits offset volumetric charges "billed on a kilowatt-hour basis," and MidAmerican's Rate IO states that the customer remains responsible for "any applicable Basic Service Charge, Demand Charge or other applicable charges approved by the Iowa Utilities Board (Board) that are not collected on the basis of delivered energy (kWh)." A fixed monthly charge survives a month in which the solar output exceeds the home's whole use, a point worked through below and the same one the true-up bill guide documents for California's utilities.
What the filed tariffs say
The Commission's page on distributed generation lists the tariffs approved under Senate File 583. For MidAmerican Energy it lists Rate IO, inflow-outflow billing of eligible distributed generation facilities, in Docket TF-2020-0235, approved November 24, 2020. For Interstate Power and Light it lists an inflow-outflow tariff, rate code IO, in Docket TF-2020-0237, approved December 30, 2020, and revisions to its net metering pilot, rate code NM, in Docket TF-2020-0238, approved the same day. The page lists an inflow-outflow tariff for each utility and no net billing tariff. The Commission notes that tariffs posted on utility websites have not been reviewed by the Commission, and MidAmerican publishes its Iowa electric tariff book as a PDF; its Rate IO sheets 374 through 384, effective November 24, 2020 in that book, are the most detailed public statement of how the method runs in practice. The table below covers MidAmerican only.
| Topic | What the sheet says | Sheet |
|---|---|---|
| Who it is open to | Eligible facilities that file complete interconnection applications on or after December 1, 2020 | 374 |
| Contract term | Twenty years; assignable for collateral purposes or in a reorganization, otherwise only with written consent that will not be unreasonably withheld | 376 |
| Interval | Fifteen minutes; each interval's net registration is inflow or outflow | 380 |
| Monthly bill | All inflow kWh in the month are summed and charged at the applicable tariffed rate, including adjustment clauses and riders; all outflow kWh are summed and credited in dollars at the outflow purchase rate | 381 |
| What the credit offsets | Applicable volumetric charges, including adjustment clauses and riders, billed on a kWh basis | 381 |
| Carry-forward | Unused credits carry forward in dollars until the end of the annual period; the Company is never required to convert them to cash | 381 |
| Annual period | Twelve consecutive monthly billing periods; the customer chooses a January or April date at interconnection; credits remaining at the end are forfeited | 382 |
| Ending service | Unused outflow purchase credits are forfeited on termination of service | 382 |
| Outflow purchase rate | The applicable retail volumetric rate, including kWh-based adjustment clauses and riders, until the Board approves a value of solar methodology and rate; the retail rate continues for twenty years | 381 |
| Renewable attributes | The Company owns and has title to the renewable energy attributes, renewable energy credits and greenhouse gas emission credits related to all outflow purchases | 383 |
| Switching from older rates | A customer on Rate NB or the Rate PG Pilot may move to Rate IO, cannot return, and loses Rate NB credits (Rate PG credits are cashed out under that tariff) | 374 |
Two lines in that table matter more than the rest for a buyer comparing offers. The first is the renewable attributes line: under Rate IO the utility takes title to the credits attached to everything the customer exports, which is a term of the contract and not a number on a bill. The second is the carry-forward line: a surplus carried from July into February is a dollar balance, so a rate that moves between the month the credit is earned and the month it is spent does not change its value. Under net billing as the statute writes it, the carried balance is in kilowatt-hours and rides whatever rate applies when it is spent.
MidAmerican's older Rate NB shows the arrangement that existed before the statute. Under that rate the net registration in kilowatt-hours carries forward as a Private Energy Credit, and the sheet adds that "The Company shall not be required to convert the Private Energy Credit to cash." Subsection 3(a)(2) of the statute requires the opposite for a utility that chooses net billing: a cash-out at avoided cost after twelve months. Subsection 8 protects the older customers by letting any customer on a net billing tariff approved on or before the availability of inflow-outflow billing continue under it "for the remaining duration of the contract regardless of any subsequent changes in ownership of such facility."
An 8 kW July, billed both ways
Every input in this example is an illustration, and none is a utility's tariff. The roof is 8 kW DC. It produces 1,050 kWh in July, 4.23 kWh per kW per day over 31 days, a planning figure and not a PVWatts run for any Iowa address. The home uses 900 kWh in the month, of which 380 kWh is used in the same interval the panels produce it. Summed over 15-minute intervals that is 520 kWh drawn from the grid and 670 kWh sent out, while a single net meter on a monthly interval sees only the 150 kWh difference between use and output. The volumetric rate is 12.0 cents per kWh with riders included, and a fixed monthly charge of $10.00 that no credit can touch. Rate plans and bill structure are covered on the sister site EnergyBS, in its utility rate plans guide.
Without solar the month costs 900 kWh at 12.0 cents plus the fixed charge, $118.00. Under net billing, the monthly interval compares use with output: 900 kWh used against 1,050 kWh produced registers 150 kWh sent out for the month, which is credited, so no kilowatt-hour is billed and 150 kWh of credit carries forward. The bill is the fixed charge, $10.00. Under inflow-outflow billing, the 520 kWh of inflow is charged $62.40 and the 670 kWh of outflow earns a dollar credit of $80.40, which wipes out the volumetric charge and leaves $18.00 carried forward. The bill is again the fixed charge, $10.00.
| Line | No solar | Net billing | Inflow-outflow, retail outflow rate |
|---|---|---|---|
| Home use (kWh) | 900 | 900 | 900 |
| Panel output (kWh) | 0 | 1,050 | 1,050 |
| Used in the same interval (kWh) | 0 | not metered separately | 380 |
| Metered flows | 900 kWh in | Monthly net: 150 kWh out | 520 kWh in, 670 kWh out (15-minute intervals, summed) |
| Energy charge on inflow | $108.00 | 0 kWh billed | $62.40 |
| Export credit | $0.00 | 150 kWh | $80.40 |
| Volumetric charge left to pay | $108.00 | $0.00 | $0.00 |
| Credit carried forward | None | 150 kWh | $18.00 |
| Fixed charge | $10.00 | $10.00 | $10.00 |
| Bill | $118.00 | $10.00 | $10.00 |
The two methods agree because the outflow purchase rate equals the retail volumetric rate and that rate is flat. A rate that varies by hour or by season would make the interval length matter, and the statute leaves both the interval and the shape of the rate to the utility's tariff; the time-of-use guide works through what that does to export value. With a flat rate, 150 kWh of credit and 18 dollars of credit are the same thing, because 150 kWh at 12.0 cents is $18.00.
The July bill also shows what solar cannot remove. Output beat use by 150 kWh and the bill still carried the $10.00 fixed charge. In a surplus month the number to watch is the carried credit, because it is what the winter draws down.
An April month and the leftover credit
Run the same arithmetic for a shoulder month where the roof does not cover the house. April output is 800 kWh (3.33 kWh per kW per day over 30 days), the home still uses 900 kWh, and 400 kWh is used in the interval it is produced. The grid delivers 500 kWh and takes 400 kWh. Net billing bills the difference, 100 kWh, at 12.0 cents: $12.00 plus the fixed charge, $22.00. Inflow-outflow billing charges $60.00 for the inflow, credits $48.00 for the outflow, and leaves $12.00 of volumetric charge, again $22.00 with the fixed charge. The two methods still agree, and the home with no solar pays $118.00.
The settlement date is where they diverge. A system built at the 110 percent ceiling for a home using 10,800 kWh a year can produce up to 11,880 kWh, a surplus of 1,080 kWh over use. If that surplus is still unspent on the January or April date, net billing cashes it out at the utility's avoided cost rate and gives the customer half. At an illustrative avoided cost of 3.0 cents, a number chosen for arithmetic and not taken from any filing, the cash-out is $32.40, the customer's half is $16.20, and the other half goes to the utility's low-income home energy assistance program. Under inflow-outflow billing the same surplus, valued at the 12.0 cent outflow purchase rate, is $129.60 in dollar credits that "shall be forfeited to the rider." The customer's net billing payout is 12.5 percent of the retail value of the energy.
Both outcomes argue against building to the ceiling. A system sized to roughly the home's annual use finishes the year near zero, and the credit it earned in summer pays the shortfall of winter. A system sized above use pays for panels whose last kilowatt-hours earn a fraction of retail or nothing. The sizing rules in the panel sizing guide work from the bill; the Iowa-specific addition is that the cost of an oversized system is a settlement rule written into a statute, not a quirk of one tariff.
The annual period also differs from a true-up in what it does. On MidAmerican's Rate IO the monthly bill already carries each month's energy charge, as the tariff table shows, so no accumulated annual bill arrives at the end of the period; the January or April date decides only what happens to credit left over. That is the reverse of the annual-billing accounts in the true-up bill guide, where charges pile up unbilled until a single settlement statement. Whether Interstate Power and Light's tariff bills the same way is a question for its own tariff sheets.
Three twenty-year clauses, kept apart
The 20-year language appears three times in section 476.49 and once more in MidAmerican's contract term, and the clauses protect different things. Treating them as one guarantee overstates what is fixed, and treating the first as a price lock misses that it fixes a formula.
Subsection 3(b)(5) reads in full: "Prior to the commission's approval of a value of solar methodology and rate, the outflow purchase rate for an eligible distributed generation facility shall be the applicable retail volumetric rate, including applicable rider charges approved by the commission and applied to non-net metered customers. The outflow purchase rate for any distributed generation facility will continue to be the applicable retail volumetric rate for a term of twenty years. Any change in ownership of such eligible facility, or adoption and use by the electric utility of a value-of-solar rate pursuant to subsection 4, shall not impact the outflow purchase rate for the distributed generation facility during the twenty-year term." What is held for twenty years is the rule that an export is paid at the retail volumetric rate. The number moves whenever retail rates move through rate cases and rider changes, in either direction, and the clause does not say when the term starts.
Subsection 4(e) is the one that locks a number: "After the commission has approved a value of solar methodology and rate, the outflow purchase rate shall be set using the value of solar methodology. The outflow purchase rate for such a facility will be fixed for a term of twenty years regardless of any subsequent changes in the electric utility's outflow purchase rate or changes in ownership of such facility." A facility that connects after approval gets the rate in force at that time, fixed for twenty years, and it does not follow later annual recomputations.
Subsection 10 is a separate protection tied to a separate threshold: "When the statewide net metering penetration level reaches ten percent, the commission shall determine whether the net billing and inflow-outflow billing methods are still reasonable and shall make recommendations to the general assembly. Regardless of the commission's recommendations, existing facilities shall continue to be eligible for the net billing or inflow-outflow billing tariff in place at the time of installation and for twenty years of operation thereafter." Ten percent is double the five percent that starts the value-of-solar proceeding, and the phrase "statewide net metering penetration level" is not the defined term "statewide distributed generation penetration" in subsection 1.
| Provision | What lasts twenty years | What can still move | Survives a sale of the home |
|---|---|---|---|
| 3(b)(5), before a value-of-solar rate | Payment of the outflow purchase rate at the retail volumetric rate, for a term of twenty years | The retail rate itself, which changes with rate cases and riders | Yes: a change of ownership does not impact the rate |
| 4(e), after a value-of-solar rate is approved | The outflow purchase rate, fixed for a term of twenty years | Nothing during the term; later annual changes apply to later facilities | Yes: fixed regardless of changes in ownership |
| 10, at ten percent penetration | Eligibility for the tariff in place at installation, for twenty years of operation thereafter | The Commission recommendation to the General Assembly on whether the methods remain reasonable | Not addressed in the subsection |
| MidAmerican Rate IO contract | The contract between the Company and the customer under the inflow-outflow arrangement | Terms the Company may revise, such as interconnection requirements "as the provisions exist and may change from time to time" (sheet 383) | Assignment only with written consent not unreasonably withheld (sheet 376) |
Three questions the statute leaves to the contract matter on a resale. First, the start of the term: subsection 10 counts twenty years of operation after installation, while 3(b)(5) and 4(e) say only "a term of twenty years" and name no start date, so the interconnection agreement is the place to find whether the clock starts at permission to operate or at the contract signature. Second, the end of the term: section 476.49 does not say what rate applies in year twenty-one. Third, the buyer: the statute says a change of ownership does not change the outflow purchase rate, and MidAmerican's contract term adds an assignment consent requirement, so the practical step at a sale is to have the utility confirm the assignment in writing. The grandfathering guide compares how California, Idaho and Illinois handle legacy status and a sale, and its test, whether the status stays with the system or with the owner, is the one to apply here.
The 5 percent and July 1, 2027 triggers
The value-of-solar clause opens subsection 4 and is short enough to quote whole: "If the commission is petitioned by an electric utility after July 1, 2027, or when the statewide distributed generation penetration rate is equal to five percent, whichever is earlier, the commission shall initiate a proceeding to develop a value of solar methodology and rate for eligible distributed generation facilities. The value of solar rate shall be determined through the use of a methodology that calculates the benefits and costs an eligible distributed generation facility provides to, or imposes on, the electric system. The value of solar methodology shall be applied independently to each electric utility. When the commission determines the value of solar methodology, it shall determine if there is a need for separate methodologies for other distributed generation technologies or if it can account for the values of other technologies with modifications to the value of solar methodology."
Several facts follow from the wording and not from anyone's forecast. The proceeding starts at the earlier of two events, a utility petition filed after July 1, 2027 or statewide penetration reaching five percent. The date marks when a petition becomes possible, and the section sets no deadline for a decision. The methodology must come from a formal proceeding and "a study conducted by an independent third party and overseen by the commission," with parties able to comment and offer testimony before adoption (paragraph a). It must include ten factors "as appropriate and supported by known and measurable evidence," listed in paragraph b: energy and fuel cost, generation capacity and reserves, transmission capacity and charges, distribution capacity, transmission and distribution line losses, fixed and variable plant operating costs, environmental compliance costs, integration costs, grid support services, and other factors based on known and measurable evidence. And it applies utility by utility, so a MidAmerican customer and an Interstate Power and Light customer could face different rates. Paragraph d requires the Commission to "consider, review, and update as appropriate" the methodology at least every three years after the initial one is complete.
The statute defines penetration in subsection 1, paragraph i: "the aggregate nameplate capacity of all eligible distributed generation facilities of electric utilities as a percentage of the aggregate peak demand of all electric utilities," and subsection 2 has the Commission publish the figure each year. The Commission's distributed generation page does so, and its 2025 table gives MidAmerican 79.1393 MW against 5,383 MW of peak demand, Interstate Power and Light 238.57 MW against 2,759 MW, and a statewide total of 317.7093 MW against 8,142 MW.
| Year | MidAmerican | Interstate Power and Light | Statewide | Statewide change, points |
|---|---|---|---|---|
| 2020 | 0.49% | 3.19% | 1.55% | not shown |
| 2021 | 0.61% | 3.92% | 1.87% | 0.32 |
| 2022 | 0.87% | 4.84% | 2.33% | 0.46 |
| 2023 | 1.10% | 5.84% | 2.78% | 0.45 |
| 2024 | 1.32% | 6.88% | 3.30% | 0.52 |
| 2025 | 1.47% | 8.65% | 3.90% | 0.60 |
The arithmetic on those figures: 317.7093 divided by 8,142 is 3.90 percent. Five percent of 8,142 MW is 407.1 MW, which is 89.4 MW or 28.1 percent more installed capacity than the 2025 table shows, if peak demand stayed where it is. The statewide figure has risen by between 0.32 and 0.60 points a year since 2020. If the next two steps each matched the last, 0.60, the series would read 4.50 and then 5.10, crossing five percent in the second of them. That sequence is arithmetic on a published series. It ignores any change in peak demand, which moves the denominator, and it ignores installation activity after the table's data.
Interstate Power and Light alone already sits at 8.65 percent, above the five percent mark, and that does not start the proceeding, because the clause counts the statewide rate. The Commission's footnotes explain how the statewide figure is built: it adds the two utilities' peak demands as an estimate because nothing filed with the Commission lets it determine a statewide coincident peak demand, and the table's inputs carry different filing dates, with Interstate Power and Light reporting on April 30, 2025 and MidAmerican's capacity coming from a report filed March 27, 2026. The peak-demand row is labelled 2024, while footnote 3 gives MidAmerican's 2025 annual peak and footnote 4 names no year for IPL's peak, so the peak-demand year may differ between the two utilities. The method and the inputs are the Commission's.
What July 1, 2027 changes
From November 3, 2026 to July 1, 2027 is 240 days. Two provisions of section 476.49 refer to that date, and no other part of chapter 476 mentions 2027. The first is that a utility petition under subsection 4 becomes possible. The second is in subsection 6: "An electric utility shall not propose treating distributed generation customers as a separate rate class in a general rate case prior to the commission's approval of a value of solar methodology or prior to July 1, 2027, whichever is earlier. If an electric utility chooses to propose a separate rate class for distributed generation customers in a future proceeding, such a proposal shall be approved or disapproved in accordance with section 476.6 and accompanying rules." After the earlier of those events, which is July 1, 2027 unless a methodology is approved first, a utility may ask for a distributed generation rate class in a rate case, and the Commission decides it under the general rate-case rules.
That second clause deserves a careful read, because the protections in subsections 3(a)(4) and 3(b)(4) are written against a comparison group: no fees or charges "that are not charged to customers in the same rate class that are not" net billing or inflow-outflow customers. A distributed generation rate class would change who is in the comparison group. The statute does not say how those clauses would apply to such a class. The question arises on the date the bar on proposing the class lifts, and the statute leaves it open.
Existing customers keep the methods and the 20-year terms described above, and the retail-rate outflow purchase rate continues for them whether or not a value-of-solar rate is ever approved.
A 2026 bill to change the trigger
House File 2672 of the 2026 session, a Commerce Committee bill formerly House Study Bill 629, was introduced on February 23, 2026 to establish a community solar program. Section 3 of the bill as introduced amended the opening of 476.49(4) by striking "If the commission is petitioned by an electric utility after" and starting the sentence "On July 1, 2027, or when the statewide distributed generation penetration rate is equal to five percent, whichever is earlier, the commission shall initiate a proceeding." That would have made the proceeding automatic on the date instead of waiting for a petition. The Legislature's bill history records the introduction and placement on the calendar on February 23, then amendments H-8171 filed March 9 and H-8209 filed March 11, and no later action. Neither amendment touches section 476.49: H-8171 caps the community solar program, and H-8209 changes a state income tax credit.
None of the 207 bills the Legislature lists as enrolled for the 2026 session contains section 476.49 in its text, so the 2026 Code wording quoted above stands. One enrolled bill does amend neighbouring sections: House File 2799, a measure on matters under the economic development authority, the utilities commission and the department of education, rewrites subsection 2 of sections 476.1A and 476.1B to add a new section 476.2(7) on sharing data for load forecasts, and leaves the exemptions in subsection 1 of each section as quoted above.
The Commission's distributed generation page, which cites a filing of March 27, 2026, restates the 5 percent and July 1, 2027 conditions in the present tense and does not mention a value-of-solar proceeding. As of November 3, 2026, the statute reads as it did in the 2026 Code, and penetration is below 5 percent on the Commission's own table.
The five percent step-down path
Subsection 4, paragraph c, is the clause that limits how fast a value-of-solar rate can fall, and it governs how a rate set by the study can behave afterward: "Upon approval of the value of solar methodology, the outflow purchase rate shall be limited to either a five percent increase or decrease from the previous outflow purchase rate. The value of solar rate shall be recomputed annually and reflected in the outflow purchase rate, limited to a five percent increase or decrease from the previous outflow purchase rate. If the utility switches from a net billing method to an inflow-outflow billing method after the value of solar methodology is approved, then the previous purchase rate shall be the applicable retail volumetric rate including all applicable rider charges approved by the commission."
On its text, the first value-of-solar rate for a utility cannot land more than five percent below the retail volumetric rate it replaces, because the outflow purchase rate before approval is the retail volumetric rate under 3(b)(5) and the paragraph limits the move from the "previous" rate. Each annual recomputation can then move it at most five percent again. Paragraph e fixes the rate for 20 years for each facility that connects after approval, so a customer who connects at step three keeps the step three rate while the next customer's rate keeps stepping. Nothing on the Commission's page shows an approved methodology, so no order has applied the clause yet, and a methodology order could read the cap differently.
The table runs the cap as arithmetic on the illustrative 12.0 cent retail volumetric rate used above. It shows the lowest outflow purchase rate a customer could receive after n annual steps if the study kept pointing lower and the cap bound every year. It is a floor the text allows, not a prediction that any step will happen, and the study could just as well point to a rate at or above retail.
| Annual steps | Rate (cents/kWh) | Share of retail | April bill | July bill | July credit carried | Value of 1,000 exported kWh |
|---|---|---|---|---|---|---|
| 0 | 12.00 | 100.0% | $22.00 | $10.00 | $18.00 | $120.00 |
| 1 | 11.40 | 95.0% | $24.40 | $10.00 | $13.98 | $114.00 |
| 2 | 10.83 | 90.3% | $26.68 | $10.00 | $10.16 | $108.30 |
| 3 | 10.29 | 85.7% | $28.85 | $10.00 | $6.53 | $102.88 |
| 4 | 9.77 | 81.5% | $30.90 | $10.00 | $3.09 | $97.74 |
| 5 | 9.29 | 77.4% | $32.86 | $10.19 | $0.00 | $92.85 |
| 6 | 8.82 | 73.5% | $34.72 | $13.30 | $0.00 | $88.21 |
| 7 | 8.38 | 69.8% | $36.48 | $16.25 | $0.00 | $83.80 |
| 8 | 7.96 | 66.3% | $38.16 | $19.06 | $0.00 | $79.61 |
| 9 | 7.56 | 63.0% | $39.75 | $21.73 | $0.00 | $75.63 |
| 10 | 7.18 | 59.9% | $41.26 | $24.26 | $0.00 | $71.85 |
In the table, July keeps its $10.00 bill through step four and starts to leak at step five, because the 670 kWh of July exports no longer cover the 520 kWh of imports. The break-even rate is 9.31 cents, 77.6 percent of retail, which lies between the fourth and fifth steps. April, which has fewer exports to begin with, starts to cost more at the first step: $22.00 at retail, $24.40 at step one, $32.86 at step five. Each 1,000 kWh exported in a year is worth $120.00 at 12.0 cents and $92.85 at step five. While the outflow credit equals the retail rate, an exported kilowatt-hour and a kilowatt-hour used at home are worth the same 12.0 cents in this model. As the rate steps down, energy used at home becomes worth more than energy sent out, and that gap is what the battery decision guide and the non-export solar guide weigh.
What to settle before a contract is signed
Three dates decide which of the clauses above governs a system. The first is the date of the complete interconnection application: MidAmerican's Rate IO applies to applications on or after December 1, 2020, and the older Rate NB customers keep their own terms under subsection 8. The second is the date any value-of-solar rate is approved for the utility, because 4(e) fixes the rate for facilities connecting after it and 3(b)(5) keeps the retail formula for the rest. The third is the January or April settlement date, which the customer picks once, at interconnection, and which sets when leftover credit is cashed out or forfeited.
A claim that net metering ends in 2027 describes a trigger date as an end date. The statute's text supports a narrower claim: from July 1, 2027, a petition for a value-of-solar proceeding is possible, and a proceeding is also required earlier if statewide penetration reaches five percent. For a buyer today, the useful question is what the interconnection contract says about the term, the rate formula and the assignment on sale, because those are the lines that the statute, the tariff and the contract each partly control. For the price side of the same quote, the quote red flags guide lists what to check.
Lines to find in an Iowa interconnection contract
- The billing method named in the contract: net billing, or inflow-outflow billing (Rate IO or rate code IO).
- The date of the complete interconnection application, and the date permission to operate was granted.
- The start date of the 20-year term, and what the contract says happens after year twenty.
- The January or April settlement date chosen at interconnection, and what happens to credit left on that date.
- The interval the utility meters on, and whether the volumetric rate varies by hour or season.
- Who owns the renewable energy credits attached to exported energy.
- The assignment clause, and what the utility needs to see when the home is sold.
- The annual usage figure the utility uses for the 110 percent test, and how it estimated production.
Iowa solar billing questions
Does Iowa net metering end on July 1, 2027?
Section 476.49 sets no end date for the billing methods. A utility petition for a value-of-solar proceeding becomes possible after July 1, 2027, and the Commission must open a proceeding earlier if statewide distributed generation reaches five percent of peak demand. Interconnected facilities are protected by twenty-year terms in three separate clauses, which the section on the three twenty-year clauses quotes in full.
What is inflow-outflow billing in Iowa?
It is the method in 476.49(3)(b): the utility meters inflow and outflow by the hour or finer, charges all applicable charges on the inflow, and credits the outflow in dollars at the outflow purchase rate. Until a value-of-solar rate is approved, that rate is the applicable retail volumetric rate. Dollar credits offset volumetric charges billed per kWh, carry forward, and are forfeited at the end of the annual period.
How close is Iowa to the 5 percent value-of-solar trigger?
The Commission's 2025 table shows statewide penetration of 3.90 percent: 317.7093 MW of eligible distributed generation against 8,142 MW of combined peak demand. Interstate Power and Light is at 8.65 percent and MidAmerican at 1.47 percent, but the statute counts the statewide rate. Reaching five percent at the same peak demand would take about 407.1 MW, roughly 89.4 MW more.
Will a value-of-solar rate apply to a system I install now?
A system that connects before a value-of-solar rate is approved stays on the retail volumetric outflow rate for its twenty-year term under 3(b)(5). The value-of-solar rate in 4(e) applies to facilities that connect after the methodology and rate are approved. When the twenty years run from, and what follows them, are contract questions.
What happens to unused credits at the end of the year?
Under net billing, excess kilowatt-hours at the end of a twelve-month period are cashed out at the utility's avoided cost rate, and the money is split evenly between the customer and the utility's low-income home energy assistance program. Under inflow-outflow billing, remaining outflow purchase credits are forfeited to the utility's rider. The customer picks a January or April date at interconnection for either method.
Does this apply to my rural electric cooperative or city utility?
Section 476.49 requires tariffs of an electric utility defined as one that is required to be rate-regulated under chapter 476. Sections 476.1A and 476.1B exempt cooperatives, small utilities and municipal utilities from the Commission's rate regulation, and neither section's list of retained matters names 476.49, unless a cooperative has elected Commission rate regulation under 476.1A(4). Those customers follow the policy their own board or council adopted.
Did the Legislature change section 476.49 in 2026?
House File 2672 would have changed the trigger so the proceeding opens automatically on July 1, 2027 or at five percent, instead of on a utility petition. The Legislature's bill history shows it introduced February 23, 2026 with amendments filed in March and no later action, and none of the 207 enrolled bills for the 2026 session contains the number 476.49.
Can I size a system larger than my usage in Iowa?
An eligible facility must have a capability to produce no more than 110 percent of the customer's annual electricity usage, and MidAmerican's Rate IO buys output above that ceiling separately under Rate AEP or Rate QF. Sizing near 100 percent of use also avoids the year-end outcome in which surplus credits are forfeited or cashed out at avoided cost.
Iowa's rule is a formula with a schedule attached. Exports are paid at the retail volumetric rate for twenty years for a system connecting now, a value-of-solar study can reset the rate for those who connect after it, and a five percent cap sets how quickly it can move. Size the roof to the home's use, read the year-end line in the contract, and treat the July 1, 2027 date as the day a petition becomes possible, not the day anything ends. Other states' export rules sit side by side on the export compensation hub.
Sources and verification
- Iowa Code 2026, chapter 476, Public Utility Regulation (legis.iowa.gov, printed December 9, 2025): Sections 476.1A, 476.1B, 476.42 and 476.49 in full: billing methods, value-of-solar trigger, 5 percent step cap, 20-year terms, rate-class bar, subsection 10. Checked November 3, 2026.
- Iowa Code 2026, section 476.49 (legis.iowa.gov, printed December 12, 2025): The single-section copy; history line 2020 Acts, ch 1004, sec 1; 2021 Acts, ch 80, sec 310; 2024 Acts, ch 1170, sec 369. Checked November 3, 2026.
- Senate File 583, enrolled, Eighty-eighth General Assembly (2020 Acts, chapter 1004): The act that created section 476.49; compared with the 2026 Code text. Bill history at https://www.legis.iowa.gov/legislation/BillBook?ga=88&ba=sf583: Senate 28 to 19 on March 18, 2019; House 98 to 0 and Senate 48 to 0 in March 2020; signed March 12, 2020; effective July 1, 2020. Checked November 3, 2026.
- House File 2672, introduced, 91st General Assembly (2026), and its bill history: Section 3 would have made the value-of-solar proceeding start automatically. History: introduced February 23, 2026; amendments H-8171 (March 9) and H-8209 (March 11); no later action. Checked November 3, 2026.
- Iowa Legislature, enrolled bills, 91st General Assembly, second session (2026), with House File 2799 as enrolled: None of the 207 enrolled bills contains section 476.49. House File 2799 amends sections 476.1A(2) and 476.1B(2) and adds 476.2(7). Checked November 3, 2026.
- Iowa Utilities Commission, On-site (Distributed) Generation: Approved tariffs (TF-2020-0235, TF-2020-0237, TF-2020-0238), the 2025 penetration table (3.90 percent statewide) and the historical series 2020 to 2025. Checked November 3, 2026.
- Iowa Administrative Code, 199-15.10 (legis.iowa.gov), ARC 9349C, effective July 16, 2025: Subrule 15.10(3): each utility offers net metering or inflow-outflow billing, or a purchase and sale arrangement at the tariffed rate. Checked November 3, 2026.
- MidAmerican Energy Company, Iowa Electric Tariff No. 2 (utility-published copy), Rate IO sheets 374 to 384 and Rate NB: Rate IO effective November 24, 2020: availability, 20-year contract, 15-minute interval, dollar credits, annual period, forfeiture, renewable attributes, 110 percent test and worked example. Utility-posted tariffs are not reviewed by the Commission. Checked November 3, 2026.
- Iowa Utilities Commission, Utility Tariffs Filed with the IUC: Links to the utilities' electric tariff pages and the statement that tariffs on utility websites have not been reviewed by the Commission. Checked November 3, 2026.
Statute quotations are from the 2026 Iowa Code (printed December 2025); the Commission's penetration table, the legislative record and MidAmerican's tariff book were checked on November 3, 2026. The worked months use illustrative production, use, rates, a fixed charge and an avoided-cost rate, and they are not a quote, a forecast or any utility's tariff. Interstate Power and Light's tariff text and the Commission's electronic docket listings are not reproduced, so IPL mechanics go no further than the Commission's list of approved tariffs. Municipal and cooperative utilities set their own policies. The step cap in 476.49(4)(c) has not been applied in any Commission order cited here, and the reading of it is the page's. Your interconnection agreement and utility tariff control. Nothing here is legal or financial advice.